1 Scope
1.1 General
This part of IEC 61850, which is a Technical Report, is intended for an audience familiar with network communication
and/or IEC 61850‑based systems and particularly for substation protection and control equipment vendors,
network equipment vendors and system integrators.
This document focuses on engineering a local area network limited to the requirements
of IEC 61850‑based substation automation. It outlines the advantages and disadvantages of different
approaches to network topology, redundancy, clock synchronization, etc. so that the
network designer can make educated decisions. In addition, this document outlines
possible improvements to both substation automation and networking equipment.
This document addresses data transfer over the network in IEC 61850, such as transmitting tripping commands for protection via GOOSE messages, and in
particular the multicast data transfer of large volumes of sampled values (SV) from
merging units (MUs).
This document considers seamless redundancy to increase the network availability under
failure conditions and the high precision clock synchronization that is central to
the process bus and synchrophasor operation.
This document is not intended as a tutorial on networking or on IEC 61850. Rather, it references and summarizes standards and publications to assist the engineers.
Many publications discuss the Ethernet technology but do not address the networks
in terms of substation automation. Therefore, many technologies and options have been
ignored since they were not considered relevant for a future-proof substation automation
network design.
This document does not address network-based security, which is the subject of IEC 62351 and IEC 62443.
This document does not address technologies for wide area networks; these are covered
by IEC TR 61850‑90‑12. Guidelines for communication outside of the substation that uses exclusively the
routable Internet Protocol have been published, especially in documents IEC TR 61850‑90‑1 (substation to substation), IEC TR 61850‑90‑2 (substation to control center) and IEC TR 61850‑90‑5 (synchrophasor transmission). However, data flows used in substation-to-substation
communication, or substation-to-control centre communication such as R-GOOSE and R-SV
are covered when they transit over Ethernet links within the substation.
This document does not dispense the responsible system integrator from an analysis
of the actual application configuration, which is the base for a dependable system.